Hi,

I am from Crossings Infra. Thanks for the update on IGL pipeline. 

I am disturbed by the comment "IGL had meetings with RWA and the builder. There are concerns raised by RWA that the IGL pipeline will damage the beautification of the common areas. No common ground could be reached". 

Assuming that the reason stated above is correct, the following are the views - 

Piped natural gas is a necessity and very beneficial for all users. I as a resident do not know when this issue was discussed with RWA. i must clarify that i am not part of GH7 RWA at this point in time. However, they should have discussed the issue in their GBM (and shared minutes of the same with all residents) before deciding on it. It is not the RWA's prerogative to unilaterally  decide on issues affecting a majority of residents without even consulting them. 

Decisions on such matters must be taken after consulting residents. The benefits of PNG will far outweigh the benefits from maintaining the beauty of the place. If some people are so concerned about beauty, they should first take care of following points - 

1. Stop people from parking their cars in places apart from their reserved ones. Cars are parked haphazardly in common areas of the society daily causing great nuisance. 
2. Stop the sewer water that flows from leakages in pipes in the basements
3. Arrange for removal of stray dogs from society premises
4. Have strict policy for people defacing lifts, spitting pan masala etc. in common areas

The list can go on forever... Important thing is to do a cost benefit analysis and then take a call rather than blocking important projects on flimsy grounds. 

As a resident of GH7, i eagerly await PNG, unless someone can convince me logically that i shouldn't. 
Regards 

Alok Agarwala


On 18 April 2013 16:06, CROMA Updates <rajubanka@gmail.com> wrote:
 

Dear Resident

Here is the update on the IGL Pipeline for the entire society on Crossings Republik from CROMA Interim Body.

1) IGL Pipeline for Home Connection 

 

Society Name

Status

Comment

Ajnara GenNext

To be Initiated

 

Amrapali

To be initiated

 

Arihant Ambience

To be initiated

 

Assotech Nest

In Progress

Builder has initiated the discussions. Construction map has been shared with IGL team. IGL has asked for one month time to review

Buland Hieghts

To be initiated

 

Clement City

To be initiated

 

Cosmos Golden Heights

 

 

Crossing Infra

Stalled

IGL had meetings with RWA and the builder. There are concerns raised by RWA that the IGL pipeline will damage the beautification of the common areas. No common ground could be reached

Divyansh

To be initiated

 

Exotica Eastern Court

To be initiated

 

Gardenia Square

To be initiated

 

Gaur Global Village

To be initiated

 

Jaipuria Sunrise Greens

To be initiated

 

Mahagun Mascot

In Progress

In advanced stage of implementation. Delayed due to a few residents have raised objection as pipeline going through their parking. The issue has been sorted out now.

Panchsheel Wellington

To be initiated

 

Paramount Symphony

Yes

Connections already functional in homes

Prateek Royal Cliff

In Progress

Builder has initiated the discussions. Construction map has been shared with IGL team. IGL has asked for one month time to review

Proview Laboni

To be initiated

 

Saviour Greenisle

To be initiated

 

ShriBalaji Foster Heights

To be initiated

 

Skytech Merion Residency

To be initiated

 

Supertech Livingstone

To be initiated

 

 

The following process needs to be initiated by the builder for IGL gas pipeline.

 

1.     Contact IGL through their marketing team for Crossings area: Led by Sonu Sharma(sonu.sharma@igl.co.in)

2.     IGL needs to be provided the layout of the society to enable their technical team (Led by Dileep Kapoor (dilip.kapoor@igl.co.in)) to propose a plan.

3.     The feasibility and the implementation of the plan is conducted by the Consultant team(Led by Manish Sah)

IGL line setup is complete around Crossings. Its upto the builders to initiate the gas pipeline. The residents of the respective societies need to request the builders to initiate the discussion with IGL. Please intimate CROMA if there is any issue in setting up a meeting with IGL.

2) IGL gas stations

The two gas stations in Crossings are ready for operations from the past few months. The roadblock is the fact that the area given on lease to IGL by Crossings management was not shown in the map to GDA for opening a gas station. The map now needs to be converted to accommodate a change of use. This is taking time.

Regards,

IT & Communication Committee

CROMA, Crossings Republik

NH-24, Ghaziabad (U.P.)




--
Alok Agarwala

__._,_.___
Recent Activity:
For latest updates do visit official CROMA website at:
http://www.croma.org.in

Also, do register at the CROMA site, if not done already:
http://www.croma.org.in/member-registration/

[IMP: People posting ads for promotion of their business or of commercial-only nature will be banned/unsubscribed without any warning or clarification]
.

__,_._,___