Re: [CROMA] Re: Saviour Greensile possession

 

Hi,
 
Last Sunday (18th November) I have also visited the site.
 
My flat is in Tower A-3 and I would like to highight the following points which I discussed with Saviour personnel (Robin) who was preset at site on Sunday:
 
1. The boundary wall is in progress and expected to be finish by December end.
 
2. The Sever linework is in progress and expected to be finish by December end.
 
3. Saviour Managemet will start sending the possession letter in December for Tower A-1, A-2 & A-3, they will give approx time of 45-60 days to get the flat registry done and to complete other GDA formaliies if any, after providing them the documents they will take another 30 - 60 days to complete the remainig work like final paint, all electrical & washroom fixtures & fittings i.e. all the necessary items to hadover complete flat, if I go by his words, we will get our ready flat by March end or in April 2013 (If all goes well and there should not be any delay in this proposed schedule).
 
4. Basic amenities like club, swimming pool, ramp, basement, yoga terrace will also be completed by April 2013.
 
5. Approach road, which is going to connect directly from main round about to NH-24 is also expected to be finish by December 2013.
 
Hoping they will work as per the schedule discussed with them, and if this is the case we can see movement of flat owners in Saviour from April 2013 onwards.
 
As recently I have shifted to crossing republic, I will keep you updated / posted through this forum.
 
Thanks & Regards,

(Praveen Antal)

From: brajesh sharma <arpbks@yahoo.com>
To: "CrossingsRepublikOwnersAndMembersAssociation-CROMA@yahoogroups.co.in" <CrossingsRepublikOwnersAndMembersAssociation-CROMA@yahoogroups.co.in>
Cc: "brajeshs@bhel.in" <brajeshs@bhel.in>
Sent: Wednesday, 21 November 2012 9:33 AM
Subject: Re: [CROMA] Re: Saviour Greensile possession

 
Good News...

I also have flat in A1 tower..Saviour are just talking since long for possession but no rays of hope before jan/Feb..i my opinion.

Hope they could manage or start at least possession letter so that we feel like we are near to our tower..:-)

Regards
Brajesh

Sent from My HTC


From: rajinder21_2000 <rajinder21_2000@yahoo.com>
To: CrossingsRepublikOwnersAndMembersAssociation-CROMA@yahoogroups.co.in
Sent: Tuesday, 20 November 2012 3:07 PM
Subject: [CROMA] Re: Saviour Greensile possession

 
Hi all

This sunday i visited Saviour Greenisle as my booking is in A1 tower.

Inside the flats doors, sanitaty work, wooden flooring and electrical fittings are pending which builder is claiming will not take much time and can be dome simultaniously when they offer posession.

Outside the flat work on boundary and front side parking was going on and enterance gate is yet to be started.

Carpeting of road from fountain chowk to saviour is still pending but electrical wire laying was under progress.

builder is claimin they will offer posession in the month of December for 3 towers.

Lets hope for the best

Regards
Rajinder Verma
9650995095
--- In mailto:CrossingsRepublikOwnersAndMembersAssociation-CROMA%40yahoogroups.co.in, bansal_pooja11@... wrote:
>
> Hi all,
> Pls update about Saviour Greensile A2 tower progress n expected date of possession.
> Thanks n Rgds,
> Pooja Bansal
>
> Sent from BlackBerry® on Airtel
>





__._,_.___
Recent Activity:
For latest updates do visit official CROMA website at:
http://www.croma.org.in

Also, do register at the CROMA site, if not done already:
http://www.croma.org.in/member-registration/